welcome to MAYFLAY

For consultation/feedback, please call the service hotline: +86-13692841862 Email:info@mayflay.com

Surface treatment Soutions

Coil Handling and Press Feeding Solutions

Safety operation regulations of decoiler!Servo feed sale

  Safety operation regulations of decoiler

  1. When starting up, first select the forward and reverse rotation after the emergency stop is turned on. The forward and reverse rotation are not selectable during operation, and the machine must be stopped first.

  2. Pay attention to maintenance, wherever there is a butter nozzle, add butter once a month. Mainly the lubrication of the bearings!

  3. Pay attention to the cleanliness of the roller surface, and do not allow welding slag, short plates or other things to fall into the roller room to avoid damage to the leveling roller.

Safety operation regulations of decoiler!Servo feed sale(图1)

  4. Pay attention to the cleanness of the roller surface, and do not allow welding slag, short plates or other things to fall into the roller room to avoid damage to the leveling roller.

  5. After using for a long time, check whether there is any loosening of the screw nut. If it is found, it needs to be tightened with a wrench. If you encounter professional problems, you must ask professionals to deal with or inquire.

  6. Establish safety awareness and pay attention to personal safety. Do not touch any rotating parts! When feeding the sheet material into the uncoiler, people's clothes or hands should not be too close to the roller. In the event of a sudden increase in the speed of the uncoiler, do not use force to drag the sheet to prevent the inertial force from being drawn into the machine.

  7. When someone inspects, repairs or refuels, you must ensure that the machine's power supply is cut off. When turning on the machine, pay attention to whether anyone is too close to the machine.

  8. The operator needs to coordinate with the feeder when operating on the operation panel. If there is a runaway phenomenon, turn off the power immediately.

  9. The operator shall not be less than three persons